Unit turnover checklist: the one we used on a real one-bedroom refresh

This is the checklist we used to turn over a one-bedroom in one of our own rental buildings in November 2026: new bathroom with a walk-in shower in place of the tub, new kitchen cabinets and faucet, fresh paint, blinds and fixtures. It covers what to do before work starts, the order trades should work in, the final test, and getting the unit rent-ready.

At the end are eight lessons we learned the hard way, including a leak that showed up after the plumber was done. No sponsored products; we run our buildings from out of state and wrote down what worked.

The unit turnover checklist

Copy it, print it, or paste it into your work order system as tasks.

Before work starts

Ordering

Work, in this order

Final test, with photo or video proof

Rent-ready

Eight lessons from our own refresh

Run the turnover like a set of work orders

This is how we run our own units in TechEdge, the software we build and use. Any work order system can do the basics.

  1. One owner per task. Not "the crew"; a name.
  2. A date on every task. When a date passes, someone hears about it.
  3. Photos as proof. Before walls close, after the finish, and the final test.
  4. Cost against the unit. Every receipt lands on the unit, so the turnover shows in your cost per door.

Frequently asked questions

What is the difference between a unit turnover and a make-ready?

A make-ready is the work that gets a vacant unit rent-ready: cleaning, paint, repairs and replacements. A turnover is the whole stretch between one tenant and the next, including the move-out inspection, the make-ready, photos, listing and move-in.

How long does a unit turnover take?

A clean-and-paint turnover can take a few days. A refresh with a bathroom conversion takes longer. On our one-bedroom, the tub-to-shower work took about a week from opening the floor to the plumber's final trim-out, and a leak at one fitting needed a return visit two days later.

In what order should trades work on a turnover?

Demolition first, then plumbing rough-in, then patching and tile, then paint, then fixtures and cabinets, then the plumber's trim-out, then a full test of every fixture. Painting before the messy trades finish means painting twice.

When should I pay the contractor?

Our rule: the plumber is paid when the trim-out is done and tested, not when the rough-in is done. Pay promptly once it passes; a record of paying fast is worth more in the next negotiation than a few days of float.

How can software help with turnovers?

Treat each turnover task as a work order: one owner, a due date, photos as proof, and the cost recorded against the unit. Then the turnover shows up in your cost per door instead of disappearing into a pile of receipts.