This is the checklist we used to turn over a one-bedroom in one of our own rental buildings in November 2026: new bathroom with a walk-in shower in place of the tub, new kitchen cabinets and faucet, fresh paint, blinds and fixtures. It covers what to do before work starts, the order trades should work in, the final test, and getting the unit rent-ready.
At the end are eight lessons we learned the hard way, including a leak that showed up after the plumber was done. No sponsored products; we run our buildings from out of state and wrote down what worked.
Copy it, print it, or paste it into your work order system as tasks.
This is how we run our own units in TechEdge, the software we build and use. Any work order system can do the basics.
A make-ready is the work that gets a vacant unit rent-ready: cleaning, paint, repairs and replacements. A turnover is the whole stretch between one tenant and the next, including the move-out inspection, the make-ready, photos, listing and move-in.
A clean-and-paint turnover can take a few days. A refresh with a bathroom conversion takes longer. On our one-bedroom, the tub-to-shower work took about a week from opening the floor to the plumber's final trim-out, and a leak at one fitting needed a return visit two days later.
Demolition first, then plumbing rough-in, then patching and tile, then paint, then fixtures and cabinets, then the plumber's trim-out, then a full test of every fixture. Painting before the messy trades finish means painting twice.
Our rule: the plumber is paid when the trim-out is done and tested, not when the rough-in is done. Pay promptly once it passes; a record of paying fast is worth more in the next negotiation than a few days of float.
Treat each turnover task as a work order: one owner, a due date, photos as proof, and the cost recorded against the unit. Then the turnover shows up in your cost per door instead of disappearing into a pile of receipts.